The voided slabs for the first half of the new bridge are in place. The contractor will be working on placing a temporary deck on the slabs and building approach ramps. Work on the welded wire faced structural earth wall has begun and will continue through late fall. Several utilities are in the process of relocating their facilities so work on the project can continue.
Tuesday, July 31, 2012
PICTURES! And an Update! July 31st, 2012
Here are some pictures from last weeks girder placement... look at the size of those things!
The voided slabs for the first half of the new bridge are in place. The contractor will be working on placing a temporary deck on the slabs and building approach ramps. Work on the welded wire faced structural earth wall has begun and will continue through late fall. Several utilities are in the process of relocating their facilities so work on the project can continue.
The voided slabs for the first half of the new bridge are in place. The contractor will be working on placing a temporary deck on the slabs and building approach ramps. Work on the welded wire faced structural earth wall has begun and will continue through late fall. Several utilities are in the process of relocating their facilities so work on the project can continue.
Tuesday, July 17, 2012
CLOSURE TONIGHT (TUESDAY - JULY 17th)
Public Works
ISSUE ALERT
WHAT: EMERGENCY ROAD
CLOSURE
WHERE: Rich Rd. S.E.
at Spurgeon Creek (by Lattin’s Cider Mill)
WHEN: 10:00 p.m. July
17th to 2:00a.m. July 18th, 2012
WHO’S INVOLVED / AFFECTED:
Emergency road closure for installation of a bypass culvert to increase
capacity of water flow due to recent storm activity. There are reader boards in place notifying
roadway users of the closure. There will
be NO thru traffic and no detour route marked.
CONTACT PERSON/PHONE NUMBER: Contractor Rognlin’s, Inc. – Ed Clevenger at
581-0860 or Thurston County Public Works Inspector Shawn Brandt at 239-2525.
Thursday, July 12, 2012
July 12th, 2012
From the field:
For the rest of the week the contractor will
continue with forms for abutments nos.1 & 2 with little interference with
traffic, although the contractor is moving in more equipment and materials for
next week when we will be in the fish window and activity will increase.
On Friday we will be pouring concrete into abutments nos.1 & 2, about 21+-
yards each which could cause slight traffic delays. Scheduled time is in the afternoon
but the contractor is trying to move the time up to 8:00 a.m. in the morning.
What this means:
Traffic impacts will increase during the week while we prepare for the time that we have permission to work in the area that would normally impact riparian life (fish).
Friday there will be some traffic delays for entry and exit of trucks and movement of equipment. Please watch for traffic control and use alternate routes to your destination if possible.
Subscribe to:
Posts (Atom)