PROJECT UPDATE JULY 23, 2013

Here is the proposed/planned 3 week schedule from the contractor:

July 22nd -26th

  •  CSBC between 71+00 and EOP
  •  Side Road Construction           
  •  CSTC between 71+00 and EOP

July 29th – Aug 2nd

  • Pave Rich Road between 71+00 and EOP            
  • Guard rail Install           
  • Pole Replacement

Aug 5th-10th           

  •  Driveway Install
  • Permanent signing            
  • Mailbox Install            
  • Edge Conditions rehab


**Note: CSBC is crushed surfacing base course and is the 1st course above the natural subgrade, CSTC is crushed surfacing top course and is a finer rock easier to form for placing the paving on top. 


Paving will be on July 30th for the first lift (driving lanes only no shoulder) and August 1st for the wearing course weather permitting. Puget Sound Energy will also be on site placing poles and crews may start signing and mailbox installation that week instead of waiting until Aug. 5th although they will still be working on this (particularly in the newer paved area) the week of Aug 5th - 10th.



Today they have placed compost in the swales and edge conditions from beginning of project to Riverwood.

Next week, (July 29th), would be a good time to plan for alternate routes of travel as paving usually clogs things up a bit.