Here is the proposed/planned 3 week schedule from the contractor:
July 22nd
-26th
July 29th – Aug 2nd
Aug 5th-10th
- CSBC between 71+00 and EOP
- Side Road Construction
- CSTC between 71+00 and EOP
July 29th – Aug 2nd
- Pave Rich Road between 71+00 and EOP
- Guard rail Install
- Pole Replacement
Aug 5th-10th
- Driveway Install
- Permanent signing
- Mailbox Install
- Edge Conditions rehab
**Note: CSBC is crushed surfacing base course and is the 1st course above the natural
subgrade, CSTC is crushed surfacing top course and is a finer rock easier to
form for placing the paving on top.
Paving will be on July 30th for the first lift (driving lanes only no
shoulder) and August 1st for the wearing course weather permitting. Puget Sound
Energy will also be on site placing poles and crews may start signing and
mailbox installation that week instead of waiting until Aug. 5th although they
will still be working on this (particularly in the newer paved area) the week of
Aug 5th - 10th.
Today they have placed compost in the swales and edge conditions from
beginning of project to Riverwood.
Next week, (July 29th), would be a good time to plan for alternate routes of travel as paving usually clogs things up a bit.