Heigh Ho, Heigh Ho, It's back to Work We go...

I'll bet you've missed us.  What?!?! Now, be nice!

Here is the {Totally Weather Dependent} schedule for the next two weeks or so.

We will start slow....


Week one:

 May 6th, Begin moving equipment back to project. Restore signs to proper locations. Return message boards to project.
May 7th, Additional remobilization, complete the rest of removal of obstructions. (fence removal)
May 8th, Grubbing Right-of-Way (This means digging up roots and vegetation beside the roadway)
May 9th, Grubbing Right-of-Way
May 10th  , Pulverizing existing asphalt from STA: 18+50 to STA: 65+00. (This is engineering talk for digging up and crushing what is left of the asphalt. From this point on, you will be on a dirt road until the paving phase of the project.)

Week two: 

May 13th , Dirt Excavation & finish wall
May 14th, Dirt Excavation
May 15th, Dirt Excavation
May 16th, Dirt Excavation
May 17th, Dirt Excavation


We will endeavor to keep you posted on the project's projected progress, via this blog and our twitter feeds @Thurston_PW and @TCPWProjects