Monday, June 10, 2013

June 10th ...

This week they plan to finish the roadway excavation for the portion that has been pulverized; which means the road will be the proper width and in the proper shape to add the next layers. 
 They will also be working on some stormwater features including culverts and drain lines into the stormwater pond.

Next week they will be finishing the first lift of crushed and starting the second lift of smaller crushed rock.

The week of June 24-28th they are planning to start paving and doing shoulder rock. This schedule is both weather dependent and dependent on soil conditions moving forward.

During paving there may be some long work days and some delays in wait time so please be patient or find alternate routes if possible.